Abbott Project Management Playbook
PDRI – Project Definition Rating Index Gate Reviews – business reviews with key stakeholders
Capital >$2.5MM
Tool & Facilitation: John Patelski
FEP deliverables completed, including risks identified FEP deliverables completed, including risks identified. Gate Review Template completed
1 week – for facilitator FEP documentation review Coordinated & scheduled by project engineer
Capital >$2.5MM
CE Gate Review templates provided
FEP Deliverable
Required For
CE Support Prerequisites Lead Time
Design Reviews – technical reviews with CE / Division engineering SMEs
Capital FUI > $5MM
Coordinate through Domingo Rubinos, Mike
FEP deliverables completed
3-6 weeks
Land (GES CE_TCOE) John Patelski
RCE Reviews
Capital >$2.5MM
FEP deliverables completed, including risks identified
3 working days – need RCE draft at start of divisional approvals 2 weeks (including CRAs)
SRA – Schedule Monte Carlo Risk Analysis CRA – Cost Monte Carlo Risk Analysis
Capital FUI > $5MM
JP Santini
MS Project MPP native file; no PDFs
Capital FUI > $5MM
JP Santini
MS Excel native file; no PDFs
2 weeks (including SRAs)