Abbott Project Management Playbook

FEP Focus

FEP Requirement - Include the Project Team’s customization of the PEG for their Project and how the team has addressed PEG Requirements.

FEP Deliverables related to PEG

• PEG Management Plan • Project Execution Plan (PEP)

8.2 G OVERNANCE •

Projects with RCE > $2.5MM (For CE Projects >$1.0MM, Divisional requirements may vary) Note: IT projects attend the BTS Gate Council meetings (see “ Stage Gate Process – Gate Council Meeting ” document for additional details.

Minimum Two (2) Assessments required:

50% Project Completion

90% Project Completion

5 KPI’s: Cost, Schedule, RFT, Deficiencies, CO’s

61